VoIP Cut Over List

Phase 1 – Port July 12 confirmed by AT&T – done Phones
IT in buildings outside of Dempsey 24
Dempsey 61
Polk Library 100
Gruenhagen 95
Horizon, Scott 60
Webster, Donner, Taylor, Evans, Stewart 50
Total 390
Phase 2 – Port July 6 confirmed by AT&T – done Phones
Clow 136
Nursing Education 113
Arts/Communication, Fredric March Theatre 121
Radford: lab, FM, faculty 40
Total 410
Phase 3 – Port July 13 confirmed by AT&T – done Phones
Student Success Center 80
Lincoln, Campus Center for Equity & Diversity, Multicultural Education Center 71
Albee, Kolf, Ceramics, HazWaste 75
Sage 185
Total 411
Phase 4 – Port July 20 confirmed by AT&T – done Phones
Halsey 103
Swart, Harrington 69
Oshkosh Sports Complex: football, baseball, softball 23
Oviatt, Pollack 15
Eric, SRWC, AWCC 95
Campus Services Center, Grounds, Auto shop, Biodigester 44
Total 349
Phase 5 – August – see below for individual Port Dates Phones
Titan Central & Heating Plant – tentatively 8/15/2017 11
Reeve construction area – tentatively 8/24/2017 42
Blackhawk, Reeve Non-Construction: info line, Central, Bookstore – tentatively 8/24/2017 76
Radford: Student Health Center – tentatively 8/25/2017 20
Fletcher – Mid-August with completion of remodel ?
COB Marathon Center – August 5 – done 6
University Police – October TBD, after e911 is installed 23
Total 222